EXECUTIVE SUMMARY: A newly acquired coffee facility was running on spreadsheets and lacked the planning structure needed for a successful SAP implementation. Catena stepped in to redesign core planning processes, strengthen master data, and build a scalable capacity model. The result was a smooth SAP go-live, stronger service performance, and meaningful inventory and cost savings.

man working on coffee production

The Challenge: Preparing a Newly Integrated Coffee Operation for SAP

After acquiring a coffee production facility, the company needed to shift from spreadsheet-driven planning to integrated, system-based processes. The operation lacked standard planning practices, safety stock logic, reliable capacity constraints, and foundational master data required for SAP-APO and ECC. Without intervention, the new business unit risked poor service, distressed inventory, and a troubled go-live.

The Solution: Building a Scalable Planning & Capacity Model

Catena’s Supply Chain Consultant partnered closely with the planning team to establish the structure, logic, and data discipline needed for SAP and for long-term operational health. Key contributions included:

Core Planning & Master Data Foundations

  • Led master data setup and governance
  • Acted as a key member of the SIOP process, transitioning items from Make to Order to Make to Stock
  • Established safety stock levels by item and velocity code (A through D)
  • Implemented Days of Supply and Days on Hand rules for all A and B SKUs
  • Reviewed the sales plan and adjusted for seasonality and limited time offerings

Inventory, Risk & Performance Management

  • Created monthly distressed inventory processes to identify expired, short-dated, or heavy DOH at the item level
  • Researched and validated demonstrated productivity rates by line, item, and carton size
  • Determined Operational Equipment Effectiveness (OEE) and theoretical maximum rates

Capacity Planning & Production Alignment

  • Developed a 24-month Rough Cut Capacity Plan
  • Determined production capacity by line and line groupings
  • Created a production and staffing plan by line / shift
  • Oversaw the execution of the sales and operations plan
  • Built detailed production line material sequencing for cartons, flavors, ingredients, and allergens

Additional Process Improvements Outside Original Scope

  • Conducted SKU rationalization for the 30% of items without minimum order quantities, reducing changeovers and eliminating unprofitable runs
  • Transitioned the facility to a closed-loop plastic pallet system to reduce quality issues and handling inefficiencies

The Benefit: Successful SAP Go-Live & Stronger Operations

Catena delivered tangible business improvements while preparing the facility for a successful system implementation:

Enabled a smooth SAP-APO & ECC integration

Reduced distressed inventory costs by $220,000

Drove case fill rate from 95.5% to 98%

Majorly reduced pallet-related issues

Additionally, our consultant received recognition from the Vice President of Supply Chain for project execution. Ready to strengthen your supply chain and system readiness? Connect with Catena Solutions to get started.